Lahaina Watershed Phase 3A

Scope of Work
The project involves the construction of a diversion channel (grassed) with an approximate length of 550 ft., a bottom width of 65 ft., depth of approximatly 14.0 ft – 15.5 ft., and side slopes of 2.5 horizontal to 1 vertical. It will also include the construction of a pre-cast concrete arch culvert crossing consisting of two (2) 20’x8’ and one (1) 32’x8’ spans with concrete slab and 4 ft. tall concrete pedestals, concrete headwalls and C.R.M wingwalls, relocation and reconstruction of an existing drainage structure, permanent irrigation system, new roadway pavement, guardrails, signs and pavement markings.
(MAP)

When
NTP (Notice to Proceed) – March 5, 2014
Completion Date - December 23, 2014
Contract Working Days: 200

Contractor
Maui Master Builders
72 Ting’s Drive
Wailuku HI, 96793

Contract Cost
$2,089,348.45

Project Contact
Construction Management administered by
AECOM Technical Services Inc
1001 Bishop Street Suite 1600
Honolulu HI 96813