Scope of Work
This project includes demolition of the existing bridge and associated structures; constructing the replacement bridge, and guard walls, reconstructing pavement areas; cold planning, installing waterline, signs, pavement markers, and striping; removal of detour road and temporary stream crossing structure; and restoration of properties of existing condition.
(
MAP)
Other Pertinent Information
Construction activities are on going. Contractor is currently removing existing bridge and other related structures.
Streets Involved
Hana Highway near mile marker 48.
Schedule
Construction is on going. Contractor given Notice to Proceed on March 12, 2012 and is expected to be complete by early of June 2013.
Contractor
Global Specialty Contractors, Inc.
5 Sand Island Access Road
Building 920,Room G
Honolulu Hawaii 96819
Contract Cost
$2,666,055.00
Project Contact
Construction management administered by
AECOM Technical Services Inc
Thomas Jenkins Construction Manager
Teddy Maulit County of Maui Public Works Engineering,
(808)270-7440