Kaholopo’o Bridge Replacement
Scope of Work
Project includes demolition of the existing bridge and associated structures; constructing the replacement Bridge, and guard walls; reconstructing pavement areas; installation of signs, pavement markers, striping and all other incidental work necessary to complete the bridge project.
(MAP)

Other Pertinent Information
Traffic will be diverted to Haneo’o Road while the bridge is being constructed. Beach parking along Haneo’o Road will be eliminated and a temporary parking will be provided.
(DETOUR ROUTE)

Streets Involved
Hana Highway (Piilani Highway on other records) near mile marker 50 and Haneo’o Road to be used as detour road during construction.

Schedule
NTP given to contractor on April 16, 2012. Detour road upgrade at Haneo’o Stream and securing temporary access to the parking lot pushed the actual project start to late March 2013. Project duration is 180 working days. Extension of completion is eminent resulting from the detour road improvements.

Contractor
Global Specialty Contractors, Inc.
5 Sand Island Access Road
Building 920, Room G
Honolulu Hawaii 96819

Contract Cost
$1,424,325.00

Project Contact
Construction Management administered by Bowers + Kubota Consulting
John Buist , CCM Construction Manager
Teddy Maulit, County of Maui Public Works Engineering (808)270-7440