Scope
This project includes replacing a portion of the existing Haiku Road culvert, Repairing the existing embankment, construction of new embankments, outlets headwall, grated inlet, 18” drain line, energy dissipater basin, concrete outlet transition, and vehicular access road, repave the existing roadway, install guardrails and provide other improvements incidental to the project.
(
MAP)
When
Contract Working Days: 180
Anticipated NTP – June 2013
Contractor
Maui Kupono Builders, Inc.
309 Kamalei Circle
Kahului, HI 96732
Contract Cost
$2,275,655.55
Project Contact
DPW Engineering Division (808)270-7745