Scope of Work
The project includes removal of existing striping and pavement markers cold planning of existing roadway, asphalt concrete pavement overlay, installing striping, pavement markers rumble strips, guardrail extension, end treatments, signage, and manhole adjustment.
(
MAP)
When
Contract Working Days: 60
NTP (Notice to Proceed) – June 3, 2013
Completion Date - Mid September
Streets Involved
Hailiimaile Road - Milepost 1.3 to Baldwin Avenue
Contractor
Maui Paving, LLC
P.O. Box 78
Honolulu, HI 96810
Contract Cost
$1,229,581.50
Project Contact
DPW Engineering Division (808)270-7745