Scope of Work
This project includes 2” cold planning and 2” resurfacing of Ala Malama Ave. (Kolapa Pl. to Malamalama Pl.). The scope of work also includes adjusting utilities, installing pavement markings, and other incidental work.
(
MAP)
When
Contract Working Days: 20
Anticipated NTP (Notice to Proceed) – April ‘13
Streets Involved
Ala Malama Avenue (Kolapa Pl. to Malamalama Pl.)
Contractor
Maui Master Builders, Inc.
72 Ting’s Drive
Wailuku, HI 96793
Contract Cost
$185,526.00
Project Contact
DPW Engineering Division (808)270-7745